如何计算确定日期的工作日数?
Posted
tags:
篇首语:本文由小常识网(cha138.com)小编为大家整理,主要介绍了如何计算确定日期的工作日数?相关的知识,希望对你有一定的参考价值。
我需要做一个像工作日计数器,但我不知道如何:
假设有人在今天04-25-2019提出请求并且需要在15个工作日内批准,即大约05-16-2019,这怎么办?我还不知道,我应该包括我国的假期。
这将是:
01-01-2019 19-04-2019 20-04-2019 01-05-2019 21-05-2019 29-06-2019 16-07-2019 15-08-2019 18-09-2019 19-09-2019 20-09-2019 12-10-2019 31-10-2019 01-11-2019 08-12-2019 25-12-2019
我试过这个:
<%
DateFrom = "10/1/2012"
DateTo = "10/31/2012"
Weekends = 0
ActualDays = 0
' Step 1: Get the actual days
ActualDays = DateDiff("d", DateFrom, DateTo)
' Step 2: Find the weekends
For x = 0 To ActualDays - 1
xDate = DateAdd("d", x, DateFrom)
If Weekday(xDate, 1) = 1 Or Weekday(xDate, 1) = 7 Then
Weekends = Weekends + 1
End If
Next
WorkingDays = ActualDays - Weekends
response.Write "ActualDays: "&ActualDays &" Weekends: "& Weekends &" WorkingDays: "& WorkingDays
%>
但它并没有按照我的意愿行事。
答案
你在正确的轨道上,你只需要检查国定假日(如果不是周末),并从实际天数减去周末和国家假日,以获得工作日数。试试这个:
' You need to keep a record of national holidays and keep it updated. Probably best to do this
' outside of your function. You can't use a constant to store an array, you could just dim a
' regular variable, but IMO a better alternative would be to use "Application" and set it in
' your global.asa file under "Sub Application_OnStart"... or just use a database.
Application("NationalHolidays") = array("01-01-2019","19-04-2019","20-04-2019","01-05-2019","21-05-2019","29-06-2019","16-07-2019","15-08-2019","18-09-2019","19-09-2019","20-09-2019","12-10-2019","31-10-2019","01-11-2019","08-12-2019","25-12-2019")
function calcDays(fromDate,toDate)
Dim ActualDays, Weekends, NationalHolidays, WorkingDays, nhIndex, x, y
fromDate = cDate(fromDate)
toDate = cDate(toDate)
ActualDays = DateDiff("d",fromDate,toDate)
Weekends = 0
NationalHolidays = 0
WorkingDays = 0
nhIndex = 0
' Loop from start day to end day
for x = 0 to ActualDays + 1
' Count the weekends
if WeekDay(DateAdd("d",x,fromDate)) = 1 OR WeekDay(DateAdd("d",x,fromDate)) = 7 then
Weekends = Weekends + 1
else
' Check for national holidays if it's not a weekend
if NOT nhIndex > uBound(Application("NationalHolidays")) then
for y = nhIndex to uBound(Application("NationalHolidays"))
' This if/else logic assumes Application("NationalHolidays") is in ascending order.
if DateAdd("d",x,fromDate) = cDate(Application("NationalHolidays")(y)) then
NationalHolidays = NationalHolidays + 1
' Keep track of the last national holiday found and start from that
' position + 1 on the next check.
nhIndex = y + 1
exit for
elseif cDate(Application("NationalHolidays")(y)) < DateAdd("d",x,fromDate) then
' Keep count of national holidays that have already passed and skip them
' on the next check.
nhIndex = y + 1
elseif cDate(Application("NationalHolidays")(y)) > DateAdd("d",x,fromDate) then
' The national holiday dates have exceeded the current date, there's no
' point in continuing checking.
exit for
end if
next
end if
end if
next
' Working days is the number of days between "fromDate" and "toDate" minus weekends and national holidays
WorkingDays = (ActualDays-Weekends-NationalHolidays)
calcDays = "<p>Actual Days: " & ActualDays & "</p>" &_
"<p>National Holidays: " & NationalHolidays & "</p>" &_
"<p>Weekends: " & Weekends & "</p>" &_
"<p>Working Days: " & WorkingDays & "</p>"
end function
response.write calcDays("29-04-2019","13-05-2019")
2019年4月29日至2019年5月13日
输出:
实际天数:14 国定假日:1 周末:4 工作日:9
编辑:要计算Date X
+ Y Working Days
= Date Z
(在您的问题中提到),您可以使用此功能:
function AddWorkingDays(startDate,workingDays)
startDate = cDate(startDate)
Dim DayCount, workingDayCount, nhIndex, isNationalHoliday, x
DayCount = 0
workingDayCount = 0
nhIndex = 0
do until workingDayCount = workingDays
' Make sure it's not a weekend
if NOT(WeekDay(DateAdd("d",DayCount,startDate)) = 1 OR WeekDay(DateAdd("d",DayCount,startDate)) = 7) then
isNationalHoliday = false ' default
' Make sure it's not a national holiday
if NOT nhIndex > uBound(Application("NationalHolidays")) then
for x = nhIndex to uBound(Application("NationalHolidays"))
' This if/else logic assumes Application("NationalHolidays") is in ascending order.
if DateAdd("d",DayCount,startDate) = cDate(Application("NationalHolidays")(x)) then
isNationalHoliday = true
' Keep track of the last national holiday found and start from that
' position + 1 on the next check.
nhIndex = x + 1
exit for
elseif cDate(Application("NationalHolidays")(x)) < DateAdd("d",DayCount,startDate) then
' Keep count of national holidays that have already passed and skip them
' on the next check.
nhIndex = x + 1
elseif cDate(Application("NationalHolidays")(x)) > DateAdd("d",DayCount,startDate) then
' The national holiday dates have exceeded the current date, there's no
' point in continuing checking.
exit for
end if
next
end if
if NOT isNationalHoliday then workingDayCount = workingDayCount + 1 ' It's a working day!
end if
' Keep count of the total number of days needed to make up the working day target
DayCount = DayCount + 1
loop
AddWorkingDays = DateAdd("d",DayCount,startDate)
end function
' As in your question, calculate 15 working days from April 25th 2019
response.write AddWorkingDays("25-04-2019",15)
2019年4月25日+15个工作日
输出:
2019年5月17日
以上是关于如何计算确定日期的工作日数?的主要内容,如果未能解决你的问题,请参考以下文章